CEPS a.s. — Solutions that fit
home / services / about us / case studies / communications / contact / facebook
english / по-русски / česky / polski

case studies


Ordering partner

LatRosTrans

Pipeline

Oil pipeline, DN 500

Place of realization

BY/LT border — Ventspils

State of realization

Lithuania, Latvia, Belarus

Date of realization

November 2022

AUTHORS OF THE ARTICLE

Adam Pařízek
Daniel Ciran

Go to the related items

  • Services
  • Case studies
  • About us
  • Communications
  • Contacts

Emptying 424 km of DN 500 oil pipeline in less than a month

The changes now taking place in the oil and gas market require fast and professional solutions. For LatRosTrans, we have emptied 424 km of the DN 500 oil pipeline using a nitrogen inerting mixture.

In less than a month, diesel fuel was safely pushed from the Belarusian border through Latvia and Lithuania to the terminal at Ventspils on the coast of the Baltic Sea. This technologically demanding operation was carried out under an EU directive to stop taking oil and oil products from Russia by the end of 2022.

It took just 2.5 months from when CEPS was first contacted by the pipeline operator in early September, followed by the development of the implementation project, to the execution and completion of all the work.

Mobile chain for the production of inerting gas mixture

Mobile membrane units for the production of nitrogen

In response to the invasion of Ukraine by the Russian army, the Council of the European Union adopted a sixth set of sanctions in June 2022, including a ban on the purchase, import or transfer of crude oil and certain petroleum products from Russia to European Union member states.

In connection with the sanctions imposed, the transportation of diesel fuel via the DN 500 Polock – Ventspils pipeline to the territories of Latvia, Lithuania and Belarus has been stopped. This created a situation in which the 596 km long DN 500 Polock – Ventspils pipeline remained filled with standing diesel fuel in its entire volume (approximately 123,600 m³).

The owner and operator of the DN 500 pipeline on the territory of Latvia is LatRosTrans, which in September 2022 (based on similar actions successfully implemented in 2010 and 2016 – Emptying and decontamination of 750 km of DN 700 pipelines) contacted again the Czech company CEPS (specializing, among others, in the displacement of oil products from pipeline systems) with the intention to displace the standing product from the DN 500 Polock – Ventspils section of the pipeline, from the Latvian-Belarusian border to the oil terminal in the location of the port city of Ventspils on the Baltic Sea coast.

Work under the contract

CEPS, as the general contractor for the contracted works, performed the oil product displacement using nitrogen.

The DN 500 pipeline route, with a total length of 424 kilometres and an approximate volume of 87,830 m³, had to be divided into six separate sections of varying lengths, the longest of which were 228 and 130 kilometres long.

The basic parameters of the individual sections are clearly summarised in the following table:

Section number

Designation

Length [km]

Volume [m³]

Linie

1

BY/LT border – Skrudaliena

8.1

1,684

main

2

Skrudaliena – Ilukste

47.4

9,804

main

3

Looping (Ilukste)

10.4

1,977

parallel

4

Musa River

0.4

77

parallel

5

Ilukste – Džukste

228.2

47,356

main

6

Džukste – Ventspils

129.8

26,932

main

Total

 

424.3 km

87,830 m³

 

After the pipeline was divided, the sections without stationary traps were temporarily fitted with special CEPS traps allowing the insertion and removal of the pigs. The excavation, installation and welding work, as well as the shutdown of the pipeline using TDW Stopple technology, was carried out by LatRosTrans.

Diesel fuel was removed of the individual sections by means of pigs that were propelled through the pipeline by on-site produced nitrogen. The production of nitrogen was provided by CEPS mobile nitrogen units.

It was necessary to produce 646,875 m³ of nitrogen to empty all six sections. The total distance between nitrogen units and the tanks located in the port of Ventspils was an impressive 358 kilometres when displaced.

The displaced diesel fuel was stored in a 50,000 m³ tank at the Ventspils terminal and pumped to the tankers.

After the product was removed from all six sections, nitrogen was left in the pipeline at a minimum pressure of three bar. This will permanently ensure a non-explosive environment in the pipeline, minimize the development of corrosion on the internal surface of the pipeline and allow monitoring of the pipeline leak tightness.

Summary

From the initial contact to CEPS by the pipeline operator in early September 2022, to the subsequent development of the implementation project, to the execution and completion of all work, only 2.5 months have passed. The diesel fuel itself was displaced from the Belarusian border through the territory of Latvia and Lithuania to the oil terminal at Ventspils on the shores of the Baltic Sea in less than a month.

The technology used, which CEPS has developed and continues to improve, enables fast, reliable and above all safe displacement of flammable liquids from pipeline systems.

Certificate of order execution and of quality of the work performed

View the certificateCertificate of order execution and of quality of the work performed


related services

The following services were provided with this project

  • All services

Pigging services – mechanical and chemical cleaning

Nitrogen services

Off-line internal inspection of pipelines

Pipeline drying

services


related case studies

See related CEPS case studies

  • All case studies

Comprehensive approach to the decommissioning of oil pipelines

Lithuania, Latvia, Belarus, Slovakia, Czech Republic
2001–2016

Off-line internal inspection of pipelines – an important tool for investment decisions

Písecko–Strakonicko, Czech Republic
2016

New approach to the results of internal inspection

Džūkste–Peteri, Latvia
2013

Oil removal and DN 700 pipeline cleaning in Latvia

Polock–Ventspils, Latvia
2010–2011

case studies


related documents

For more documents and other information, see the section about us

  • All about CEPS

LatRosTrans Certificate of order execution and of quality of the work performed

Discharging 424 km of DN 500 oil product pipeline using a nitrogen mixture

Technical specifications CZ

about CEPS


related communications

Read articles related to this case study

  • All articles

CEPS again in the Baltics

PETROL Magazín 1 / 2023

Comprehensive approach to the decommissioning of oil pipelines

Pipeline Technology Journal 4 / 2017

Lithuania wins independence of Russian natural gas supplies, and we were there! CZ

Plyn 12 / 2014

communications


contact

If you have any questions, do not hesitate to contact CEPS responsible persons

  • Contact us

Aleš Brynych

general manager – CEO

phone +420 241 021 547

info@ceps-as.cz

Filip Tesař

sales manager

phone +420 606 641 328

info@ceps-as.cz

CEPS a.s. Head office

phone +420 241 021 511
fax +420 241 021 512

e-mail info@ceps-as.cz

see all contacts and maps


© 2013–2025 CEPS a.s. / Technical specifications CZ / Contacts